Kanban's Survivability Agenda and Antifragility

A conversation on the kanbandev online forum has triggered this post. The discussion concerns how evolutionary change is applied, particularly when the fitness landscape is changing to such a degree that large rather than small steps are needed to survive in the new competitive environment. It got me thinking that we must consider evolutionary change on more than one level if we want to address what the Kanban Method calls its Survivability Agenda.

The first mystery to consider is how evolution jumps across valleys in the fitness landscape. Seems to me there are 3 possibilities. You could make large leaps in what you think are promising directions. Doesn't sound a great idea because you're doing reasonably well as you are (different if you know you face an imminent existential threat, but it has the same likely outcome). You could wait for the peak you're climbing to decline in the fitness landscape, to the stage when small steps will move you off it. That's probably going to be too late. Or you rely on diversity. Your peak may be declining and you may - if trends continue - be doomed, but others are in better spaces and they will grow.

The final option sounds like disaster. But I think it is the way evolution works. Processes and technologies evolve much faster than biological organisms (see Eric Beinhocker's Origin of Wealth for more discussion of this) because the cycles of copying with differences, selection, amplification/damping are much shorter. Not only that, they are accelerating, which is what is now so threatening to large organisations. Does this mean large organizations must sit back and let the inevitable happen? Of course not. The key is to have multiple fragile parts, so the organization itself is more antifragile.

In Antifragility N N Taleb discusses how hierarchies can gain antifragility by allowing fragility within them. And also how natural antifragility can be irresponsibly eroded, if higher structures in the hierarchies (like governments) absorb the fragility of structures within them (like banks). Back to the Dinosaurs - they were antifragile as a species (genus? - I don't know; biologists please excuse) to most changes in the fitness landscape less than massive climate change. But since that was the limit of their antifragility they died out. But the higher level in the hierarchy (life on earth) survived (just) because there were some funny rat-like creatures running around scratching a living beneath the dinosaurs feet. They found themselves in the foothills of some pretty small peaks of the fitness landscape, and made the most of it.

So the levels in the hierarchy of Kanban (e.g. Personal, Team, Product, Portfolio) and its stress on the exploitation of real options, are keys to its "Survivability Agenda".* Portfolio management is key. It is where antifragility of the organisation can be built or lost. Portfolio Management must decide what level of investment different products and product ideas receive, and for how long before the return must be tangible. In a stable fitness landscape they might consider that the one successful product they have, should receive all the investment. This builds a monoculture which is vulnerable to shifts in the landscape. Keeping options has a cost but preserves the antifragility at the higher scale. Diversity within the organization and a culture which encourages innovation, learning and experimenting will build greater survivability. Note that in part this is because it tolerates and encourages more fragile technologies and processes within it. They are limited in their ability to survive - indeed they need to maintain the differences from more successful instances, precisely so that diversity is preserved. Eric Bienhocker has an excellent account of Microsoft's use of options when developing Windows. They also had teams investing in OS/2, Apple and Unix. Clearly it would not have been helpful if the Unix team say, thought the OS/2 option was better and started working on that instead of Unix.

In summary, I don't think Kanban provides any magic bullets here. Hopefully it exposes the issues in building resilient or antifragile organisations but it is down to the strategists, managers and leaders within these organisations as to how the tools and insights might be applied. Different groups make different choices. There is no recipe. That in my opinion why it remains one of the most interesting and important methods around.


Post a Comment

Popular posts from this blog

Does your Definition of Done allow known defects?

Is it just me or do you also find it odd that some teams have clauses like this in their definition of done (DoD)?
... the Story will contain defects of level 3 severity or less only ... Of course they don't mean you have to put minor bugs in your code - that really would be mad - but it does mean you can sign the Story off as "Done"if the bugs you discover in it are only minor (like spelling mistakes, graphical misalignment, faults with easy workarounds, etc.). I saw DoDs like this some time ago and was seriously puzzled by the madness of it. I was reminded of it again at a meet-up discussion recently - it's clearly a practice that's not uncommon.

Let's look at the consequences of this policy. 

Potentially for every User Story that is signed off as "Done" there could be several additional Defect Stories (of low priority) that will be created. It's possible that finishing a Story (with no additional user requirements) will result in an increase in…

"Plan of Intent" and "Plan of Record"

Ron Lichty is well known in the Software Engineering community on the West Coast as a practitioner, as a seasoned project manager of many successful ventures and in a number of SIGs and conferences in which he is active. In spite of knowing Ron by correspondence over a long period of time it was only at JavaOne this year that we finally got together and I'm very glad we did.

Ron wrote to me after our meeting:

I told a number of people later at JavaOne, and even later that evening at the Software Engineering Management SIG, about xProcess. It really looks good. A question came up: It's a common technique in large organizations to keep a "Plan of Intent" and a "Plan of Record" - to have two project plans, one for the business partners and boss, one you actually execute to. Any support for that in xProcess?

Good question! Here's my reply...

There is support in xProcess for an arbitrary number of target levels through what we call (in the process definitions) P…

Understanding Cost of Delay and its Use in Kanban

Cost of Delay (CoD) is a vital concept to understand in product development. It should be a guide to the ordering of work items, even if - as is often the case - estimating it quantitatively may be difficult or even impossible. Analysing Cost of Delay (even if done qualitatively) is important because it focuses on the business value of work items and how that value changes over time. An understanding of Cost of Delay is essential if you want to maximise the flow of value to your customers.

Don Reinertsen in his book Flow [1] has shown that, if you want to deliver the maximum business value with a given size team, you give the highest priority, not to the most valuable work items in your "pool of ideas," not even to the most urgent items (those whose business value decays at the fastest rate), nor to your smallest items. Rather you should prioritise those items with the highest value of urgency (or CoD) divided by the time taken to implement them. Reinertsen called this appro…